Proposed Contractual Schedule

Indicative lead time: 18 to 26 weeks after order, down payment, input data and approved Design Freeze. Mechanical / electrical installation depends on the shutdown windows communicated by Tongon.

08 · Gantt chart

Six phases, four payment milestones

W0
W5
W10
W15
W20
W25

W0 – W2

Kick-off, site visit, data collection and surveys

3 wks

W3 – W5

Detailed engineering, design review, Design Freeze

3 wks

W6 – W17

Procurement, cabinets, configuration, FAT preparation

12 wks

W18 – W20

FAT, shipping and logistics

3 wks

Per shutdowns

Mechanical / electrical installation in batches

~4 wks

+2 to 4 wks

SAT, baselines, training and initial stabilization

2–4 wks
Payment milestones
30 %Order & mobilization
40 %After Design Freeze / before shipping
20 %End of on-site installation
10 %SAT and DOE

Note: weeks counted from order placement (W0). The installation phase (hatched) and final stabilization follow the machine shutdown schedule communicated by the client — their exact position on the axis is indicative.