Schedule · Online Condition Monitoring System
Proposed Contractual Schedule
Indicative lead time: 18 to 26 weeks after order, down payment, input data and approved Design Freeze. Mechanical / electrical installation depends on the shutdown windows communicated by Tongon.
08 · Gantt chart
Six phases, four payment milestones
W0 – W2
Kick-off, site visit, data collection and surveys
W3 – W5
Detailed engineering, design review, Design Freeze
W6 – W17
Procurement, cabinets, configuration, FAT preparation
W18 – W20
FAT, shipping and logistics
Per shutdowns
Mechanical / electrical installation in batches
+2 to 4 wks
SAT, baselines, training and initial stabilization
Note: weeks counted from order placement (W0). The installation phase (hatched) and final stabilization follow the machine shutdown schedule communicated by the client — their exact position on the axis is indicative.